To meet the requirements od a production order the user can either visually look at the order to see if it can be built by looking at the colored indicators.

Green – on the top item means that all components or sub-assemblies are available to proceed.
Yellow – means that this production order can be built but at least one component is over-committed elsewhere. Once built other orders may now be short.
Red – tells the user that one or more components are not available. In company settings/Inventory if “Prohibit overshipping” is checked, then the user cannot build.

To get a printed version of shortages, click on the print icon and select “Production Trial Build” report.

Once a production order has been scheduled the company would normally print a ‘Production Order’ also know as a traveler.