To determine whether or not a production order can be built, and an indication of what is preventing the build, there are visual cues on the order details with colored indicators for each item.

For each component item, the indicator shape is a circle and the colour means:

Green – There is enough quantity on hand to fulfill this production order and all other outstanding production orders that use this component.
Yellow – There is enough quantity on hand to fulfill this production order, but the total quantity committed exceeds the quantity on hand. All production orders that use this component cannot be built.
Orange – There is not enough quantity on hand to fulfill this production order, but a purchase order has been issued for this component item that will allow building the order once the item is received. This production order cannot be built unless the Company Setting in Inventory for Prohibit Overshipping is disabled.
Red – There is not enough quantity on hand to fulfill this production order. This production order cannot be built unless the Company Setting in Inventory for Prohibit Overshipping is disabled.

The status indicator for the item to be built or any sub-assembly items has a square shape instead of a circle. The colour is determined from the highest unavailability status of the component items within.

To get a printed version of shortages, click on the print icon and select “Production Trial Build” report.

Once a production order has been scheduled, it is typical to print the ‘Production Order’ report, also know as a traveler.